Salem council votes 7-2 to swap a data center power cap for a 60,000-square-foot size limit

The Daily Salem teamFrom today’s edition · 1 min read · 4 sources

ShareEmailFacebookX

If you've followed the fight, new rules are moving forward, but they aren't final. Salem City Council voted 7-2 Monday to swap a proposed 10-megawatt power cap for a 60,000-square-foot building limit on future data centers. Councilors also voted unanimously to advance the wider package, after amending staff recommendations several times.

Verrus's Oakline at Mill Creek plan totals 600,000 square feet, so it couldn't proceed as designed under the new limit. But the company applied July 31, and Oregon land-use law generally applies the rules in place then. The council's Nov. 17 zoning interpretation is the bigger hurdle.

Verrus's plan is 10 times the proposed size limit

Source: Salem Business Journal

View as table
Value
Verrus's proposed buildings600K sq. ft.
Proposed size limit60,000 sq. ft.
  • Survey: 61% of 346 respondents backed prohibiting large hyperscale centers
  • Council supported banning diesel backup generators at covered facilities
  • Not law yet: Ordinance Bill No. 17-26 heads to second reading

Councilor Paul Tigan introduced the size limit, arguing it puts Salem on stronger legal footing. City planner Bryce Bishop said a 60,000-square-foot facility could use five to 12 megawatts. Staff had described the proposed amendments as an interim measure until more recommendations arrive.

Salem's data center rules are still moving

  1. July 31 submits its application for Oakline at Mill Creek
  2. Nov. 17Council interprets existing zoning as excluding certain AI and hyperscale data centers
  3. Nov. 23Council votes 7-2 for a 60,000-square-foot limit in place of the power cap
  4. Dec. 14City staff are expected to present revised ordinance language
  5. Oct. 2027Latest date the council agreed to revisit the data center regulations

Sources: Salem Business Journal, Statesman Journal, Salem Reporter

Read it in the full edition

More from today’s edition

Read the edition
All city hall news
  1. Salem Reporter13 hours ago

    CITY MEETING: Councilors disagree on certain details but move forward on regulating data centers, on Salem Reporter

    On Monday, the Salem City Council discussed how to best regulate data centers, ultimately voting unanimously to advance a plan to change outdated city zoning laws. The council was split on whether the city’s new codes should limit the use of diesel backup generators, or whether regulations should focus on capping electricity usage or limiting square footage. A final decision on the matter is expected next month. To comment on this story, use the form at the end of the report.

  2. Salem Business Journal16 hours ago

    Salem Moves to Replace Data Center Power Cap With 60,000-Square-Foot Limit, on Salem Business Journal

    Salem data center regulations could limit facilities to 60,000 square feet, affecting Verrus and future investments from companies like Google and OpenAI.

  3. Statesman JournalNov. 23

    Salem City Council extends Detroit drawdown emergency declaration, on Statesman Journal

    Salem City Council voted Nov. 23 to extend an emergency declaration relating to the planned deep drawdown of Detroit Reservoir to Dec. 31, 2027.