Salem council votes 7-2 to swap a data center power cap for a 60,000-square-foot size limit
Verrus's plan is 10 times the proposed size limit
Source: Salem Business Journal
View as table
| Value | |
|---|---|
| Verrus's proposed buildings | 600K sq. ft. |
| Proposed size limit | 60,000 sq. ft. |
If you've followed the Verrus fight, new rules are moving forward, but they aren't final. Salem City Council voted 7-2 Monday to swap a proposed 10-megawatt power cap for a 60,000-square-foot building limit on future data centers. Councilors also voted unanimously to advance the wider package, after amending staff recommendations several times.
Verrus's Oakline at Mill Creek plan totals 600,000 square feet, so it couldn't proceed as designed under the new limit. But the company applied July 31, and Oregon land-use law generally applies the rules in place then. The council's Nov. 17 zoning interpretation is the bigger hurdle.
- Survey: 61% of 346 respondents backed prohibiting large hyperscale centers
- Council supported banning diesel backup generators at covered facilities
- Not law yet: Ordinance Bill No. 17-26 heads to second reading
Councilor Paul Tigan introduced the size limit, arguing it puts Salem on stronger legal footing. City planner Bryce Bishop said a 60,000-square-foot facility could use five to 12 megawatts. Staff had described the proposed amendments as an interim measure until more recommendations arrive.
Salem's data center rules are still moving
- July 31Verrus submits its application for Oakline at Mill Creek
- Nov. 17Council interprets existing zoning as excluding certain AI and hyperscale data centers
- Nov. 23Council votes 7-2 for a 60,000-square-foot limit in place of the power cap
- Dec. 14City staff are expected to present revised ordinance language
- Oct. 2027Latest date the council agreed to revisit the data center regulations
Source: Salem Business Journal