City HallTop story
Salem City Council votes Tuesday on whether city code allows AI data centers
Salem's data center decisions run from Nov. 17 to Nov. 23
- Nov. 6Verrus CEO offers the city a $10 million community benefits package.
- Nov. 17Council will deliberate and vote on whether the zoning code allows AI data centers.
- Nov. 23A public hearing on longer-term data center rules is scheduled.
Sources: 1430 KYKN, Salem Reporter
If you've followed the Verrus data center fight, the Salem City Council is about to deliberate and vote online on whether the city's zoning code allows AI data centers. That includes the proposed Oakline at Mill Creek project in southeast Salem.
- Vote: Tue., Nov. 17, online
- Watch: the city's YouTube livestream, starting at 6 p.m.
- Next: Nov. 23 hearing on data center and battery storage rules
City Attorney Dan Atchison said in a report to the council that the code only includes guidelines for conventional data centers. When the term was added in 2013-2014, he said, AI and hyperscale data centers were rare in Oregon. The council would adopt a code interpretation, not a code amendment, and it would apply to Verrus' pending application.
$10 millionVerrus' community benefits offer to Salem
The details of the proposed agreement were sent to the entire Salem City Council.
Source: Salem Reporter
Verrus CEO Nelson Abramson offered the city that package. Hundreds of people have testified against the Verrus data center and other AI data centers, and the council has already enacted a moratorium on data center construction.