City HallFriday, November 13
Salem pushes its AI data center vote to Tuesday, and testimony is open until 5 p.m. today
The Daily Salem team
If you've got something to say about Salem's AI data center rule, you have until 5 p.m. today, Fri., Nov. 13, to send it. The City Council was set to vote Thursday on Resolution 2026-46, but the meeting was rescheduled to Tue., Nov. 17. City spokesperson Rob Layne said the move gives residents enough time to submit testimony after Microsoft Outlook, the city's email client, went down.
The data center vote lands Nov. 17, with more steps to follow
- July 31The Oakline at Mill Creek application was submitted.
- Nov. 13Public testimony is due by 5 p.m.
- Nov. 17Council will deliberate and vote on Resolution 2026-46.
- Nov. 23A public hearing is set on long-term data center and battery storage rules.
- Jan. 2027The deadline to answer the listed deficiencies in the Oakline application.
Sources: 1430 KYKN, Salem Business Journal, Salem Reporter
The resolution would interpret Salem's zoning code as excluding AI and hyperscale data centers from permitted uses. It's tied to Verrus' proposed Oakline at Mill Creek campus in southeast Salem, about 600,000 square feet across two buildings. City Attorney Dan Atchison says it's an interpretation, not an amendment, which would take a more extensive process. The developer argues it's a zoning change that requires added legal procedures.
The proposed Oakline campus would cover about 600,000 square feet
Floor area of the proposed Oakline campus, beside places you know
10 football fields would fit inside the proposed Oakline campus
Source: Salem Business Journal
View as table
| Floor area | |
|---|---|
| The proposed Oakline campus | 600,000 sq. ft. (Two buildings) |
| A football field | 57,600 sq. ft. (end zones included) |
| A Walmart Supercenter | about 180,000 sq. ft. |
- Earlier votes: moratorium, ban on NDAs with data center developers
- Hundreds testified against the Verrus project and other AI data centers
- Resolution opponents, including business groups, warn of uncertainty for developers
Sources: Salem Reporter, 1430 KYKN, Touchdown Wire, Salem Business Journal