City HallTop story
Salem City Council delays its vote on a rule that could block the Mill Creek data center
The council's data center decision is now set for Thursday
- Sept. 21Council adopts a separate 120-day moratorium on certain data center construction.
- Nov. 9Council postpones deliberations on Resolution No. 2026-46 after public testimony.
- Nov. 12Council will resume deliberations at a virtual special meeting at 6 p.m.
Salem City Council hit pause Monday night on a vote that could block Verrus' Oakline at Mill Creek AI data center. After more than two hours of testimony on Nov. 9, councilors voted 7-0 to close the public hearing and keep the written record open. City Attorney Dan Atchison proposed the delay to give councilors time with a large amount of written testimony.
At issue is Resolution No. 2026-46, which would read "data center facilities" in city code as excluding AI and hyperscale data centers. Atchison said none were in Salem or western Oregon when the term was added in 2013-2014. The resolution wouldn't decide Verrus' application for 4720 Mill Creek Drive SE, but later city decisions would have to follow it.
- Next meeting: Thu., Nov. 12, 6 p.m., virtual special meeting
- Oral hearing: closed. Written record: still open
- City staff: expected to address testimony before a decision
Business and labor representatives raised concerns about jobs and permitting certainty, while residents questioned electricity demand and water use. Verrus CEO Nelson Abramson said in written testimony the company is offering to enter a Community Benefits Agreement that he said would set enforceable caps on water, noise and power.
The dollars and days behind the data center fight
- $5 billion
- in potential investment previously described for the project, or more
- $10 million
- in investment Verrus offers in a Community Benefits Agreement
- 120 days
- length of the data center moratorium adopted Sept. 21