City HallWednesday, November 18
Salem City Council votes 6-2 to read city code as excluding AI data centers
The Daily Salem team
If you've followed the Verrus data center fight, here's where it stands. Salem City Council voted 6-2 Tuesday night to interpret the zoning code as excluding AI and hyperscale data centers. The Statesman Journal reports the vote effectively halts the Verrus project planned for the Mill Creek Corporate Center. Salem Reporter says it could complicate that project.
Six councilors voted to exclude AI data centers from city code
Salem City Council vote, Nov. 17
6–2
Clarify existing city code to exclude AI and hyperscale data centers
Yes 6
- Nishioka
- Tigan
- Brown
- Vang
- Nordyke
- Varney
No 2
- HoyMayor
- Gwyn
Absent 1
- Matthews
Source: Statesman Journal
View as table
| Member | Seat | Vote |
|---|---|---|
| Linda Nishioka | Yes | |
| Paul Tigan | Yes | |
| Irvin Brown | Yes | |
| Mai Vang | Yes | |
| Vanessa Nordyke | Yes | |
| Micki Varney | Yes | |
| Julie Hoy | Mayor | No |
| Deanna Gwyn | No | |
| Shane Matthews | Absent |
The meeting was virtual because of a scheduling conflict at Loucks Auditorium, and the council took no public testimony, though thousands of pages were submitted. Verrus had also offered Salem a community benefits package. CEO Nelson Abramson said the company is "disappointed by tonight's vote" but "we remain committed to Salem."
- Next: public hearing on longer-term data center zoning, Nov. 23
- Also on Nov. 23: rules for battery energy storage facilities
- Delay: Microsoft Outlook outage pushed the Nov. 12 meeting to Nov. 17
$10 millionin investment Verrus promised in a proposed Community Benefits Agreement
Abramson said the agreement would be enforced through a development agreement with Salem.
Sources: 1430 KYKN, Statesman Journal
Sources: Salem Reporter, Statesman Journal, 1430 KYKN